Jun 14, 2022 | Project Updates
Lake Pleasant Road, from Imlay City Road to Lum Road will be closed to thru traffic on Saturday, June 18, 2022, for the first lift of Asphalt Paving Operations. Please seek alternate routes, or follow the posted detour for the safety of the construction crew. The...
Jun 14, 2022 | Project Updates
Daley Road will be closed to thru traffic later this week for Asphalt Paving Operations on Friday and Saturday (June 17 – 18, 2022). Please seek alternate routes, or follow the posted detour for the safety of the construction crew. Shoulder material will be...
Jun 14, 2022 | Project Updates
Oregon Road will be closed to thru traffic this week for Asphalt Paving Operations on Wednesday and Thursday (June 15 – 16, 2022). Also, during the paving operations, the Contractor will be adjusting water main manhole covers. Please seek alternate routes, or...
Jun 9, 2022 | Project Updates
Average Daily Traffic (ADT) Counts will start Monday, June 13, 2022, in Marathon Twp. Data will be collected on all roads within the Township. It is expect to take about three (3) weeks to complete. Hoses will be placed across the roadway to count vehicles as they...
Jun 9, 2022 | Project Updates
The Lapeer CRC Contractor is scheduled to start crushing the existing asphalt on Oregon Road, Elba Road easterly to Indian Road, on Monday, June 13, 2022. During the crushing process the Contractor will pulverize the existing asphalt road to create a loose gravel...
Jun 9, 2022 | Project Updates
The Lapeer CRC Contractor will start milling operations along Daley Road, from Lapeer Road M-24 easterly to Fish Lake Road, on Friday, June 10 to Saturday, June 11, 2022. The removal of the existing asphalt in select locations is being done in preparation of the...
Jun 9, 2022 | Project Updates
The Lapeer CRC Contractor will start milling operations along Lake Pleasant Road, from Imlay City Road northerly to Lum Road on Friday, June 10 to Saturday, June 11, 2022. The removal of the existing asphalt in select locations is being done in preparation of the...
Jun 9, 2022 | Project Updates
Lake Pleasant (N) Road Contractor (Burnside Road north to M-90) is scheduled to pave the road and approaches from Monday, June 13 to Thursday, June 16, 2022, weather dependent. Aggregate shoulders and driveway approaches are scheduled to be completed after the...
Jun 9, 2022 | Project Updates
Burnside Road Contractor is scheduled to finish the eastbound lane and approach paving today, Thursday, June 9, 2022. Aggregate shoulders and approaches are scheduled to be completed during the week of June 13, 2022. Restoration of topsoil, seed and mulch will be...