Lapeer County Road Commission

Road Projects & Construction


June 23, 2016

- Grading Hunters Creek and Lake George.
- Mowing in Almont, Deerfield and Imlay Townships and on I-69.
- Crack sealing Farnsworth Road north of Daley Road.
- Ditching on Sutton Road in Metamora Township, Hough Road in Dryden Township and in District 3.


 

 

Projects at a Glance
Below is a list of projects expected to begin in 2016.

Projects in 2016 - as of 01/29/16

 


 

Current Projects & Construction - LCRC


1. Columbiaville Road Reconstruction
Reconstruction of Columbiaville Road from M-24 to Lonsberry Road is scheduled to start after 4th of July Holiday. Work consists of drainage improvements, crushing and reshaping Columbiaville Road and bituminous paving. Questions, concerns and comments shall be directed to Lapeer County Road Commission - Destain Gingell, P.E., County Highway Engineer at 810-664-6272 ext. 311 or dgingell@lcrconline.com.

2. Millville Road Reconstruction
Reconstruction of Millville Road from Oregon Road to just north of Reamer Road is scheduled to start after the 4th of July Holiday. Work includes installing of a center turn lane. Work is anticipated to be completed by Labor Day weekend. Questions, concerns and comments shall be directed to Lapeer County Road Commission - Destain Gingell, P.E., County Highway Engineer at 810-664-6272 ext. 311 or dgingell@lcrconline.com.

3. North Lake Road and Otter Lake Road Intersection
Intersection reconstruction work at North Lake Road and Otter Lake Road is scheduled to start after Labor Day weekend. Questions, concerns and comments shall be directed to Lapeer County Road Commission - Destain Gingell, P.E., County Highway Engineer at 810-664-6272 ext. 311 or dgingell@lcrconline.com.


 

 

 

Projects - Other Jurisdictions

 



1. Bridge work along I-69
MDOT will complete repairs and improvements to 11 bridge structures in Lapeer County. Beginning Friday, April 15, crews will start work on the underside of Wilder Road, Five Lakes Road, Lake George Road and Lake Pleasant Road over I-69. This will require single-lane closures on eastbound and westbound I-69 from Lake Pleasant Road to Wilder Road.
Additional lane closures can be expected later this year while crews continue structures, including top side of the bridges. The estimated completion is September 2016.
**(05/24/2016) Beginning June 6th crews will start work on the bridge decks of Lake George, Lake Pleasant and Morris Road. Both Lake George and Lake PLeasant Road will have temporary signals maintaining one lane of altering traffic. Morris Road will be closed and detoured using Newark, Clark, and Higley Roads.
Questions and concerns may be directed to MDOT, Jacelyn Hall 989-245-7117

 

2. KWA Water Pipeline
Construction began Wednesday April 22, 2015 on the KWA water pipeline.

KWA 4005
60 inch line pipe installation was completed on 06/10/16 on Kings Mill Road and Clear Lake Road. The contractor will continue to install cross culverts on Lake Pleasant Road, Kings Mill Road and Clear Lake Road. This work may temporarily close the roads while the culverts are being installed. This work will carry on until the completion of culvert installations which is expected to be approximately the second week of July. The contractor will concentrate all efforts on restoring the roads and ditches and performing restoration until the intended work is complete.

KWA 4006
Pipe installation was complete on 06/06/16 on Stanley Road. The contractor will continue to install cross culverts on Stanley Road and Klam Road for the next week. This work may temporarily close the roads while the culverts are being installed. The contractor is anticipated to begin road restoration work on Klam Road as soon as 06/17/16, this work is weather dependent. The contractor will continue road restoration operations and ditch restoration along Norway Lake Road West of M-24 during this time. The remaing road restoration work will begin approximately the second week of July. This work will continue until the intended road work is complete.

KWA 5004
The intersection of Stanley Road and German Road will be set up to close Thursday morning June 16, 2016 for stage 4 of the project. The closure may last into the month of July. Stanely Road will remain closed to through traffic between German Road and Marathon Road.

Questions, concerns and comments can be directed to the Genesse County Drain Commission 810-732-7870

Genesee County Drain Commission
Karegnondi Water Authority

 

 

 

 

 

 

 


 
Home | About Us | Policies | Traffic Counts | Road Projects | Meetings | Bids and Projects | Forms and Permits | Service Request
FAQ | Location Maps | Employment | Contact Us | Links
| Dashboard